Rake Task Ordering
Suppose I have two top-level tasks:
task :publicBuild => [:zipSourceCode, :copyPrivateKey]
task :internalBuild => [:copyPrivateKey]
For the internalBuild
task, I don't want to zip source code - I just want the private key. But for a p开发者_高级运维ublicBuild
, I want to do both. But I need to guarantee that for the publicBuild
, the zipSourceCode
task is executed before the copyPrivateKey
task (I don't want the source code ZIP to contain the public key).
A dependency such as copyPrivateKey => zipSourceCode
wouldn't work because it would mean that for internalBuild
, it would call zipSourceCode
, which I don't want.
What I want to tell rake is "if these two tasks are to be executed, you should do this one first, but they are both optional". Is this possible?
As floyd said... the tasks should be performed in the order in which they appear in the dependency array.